  • Brucejack Mine Substation

    Brucejack Mine Substation

    Westpark again teamed with Wildstone Construction and Struthers Technical Solutions in 2016 to achieve the contract for the BruceJack substations. A total of three stations, along with ancillary services were constructed, including a 138kV tap station at the point of interconnection, a 138kV x 69kV station that feeds the processing facilities, and an indoor 69kV […]

  • Canoe Creek Hydro Company

    Canoe Creek Hydro Company

    The Canoe Creek Hydro Project is a 5.5MW run-of-river project, West of Port Alberni in central Vancouver Island. Westpark Electric Ltd. was contracted to provide installation services for the electrical and mechanical systems for the plant, including the substation and short 69kV transmission line design and install. Owner: Canoe Creek Hydro Company Client: Canoe Creek […]